Chapter 1 of 1 · 45 min read

Time and Work — Complete Guide

Table of Contents

  1. Introduction to the Topic
  2. Basic Concepts and Terminology
  3. Core Formulas
  4. The LCM (Total Work) Method — The Master Technique
  5. Type 1: Individual Efficiency Problems
  6. Type 2: Two or More Persons Working Together
  7. Type 3: Work Left / Work Done in Parts (Alternate Days)
  8. Type 4: Men, Women, Children — Comparative Efficiency
  9. Type 5: Work and Wages
  10. Type 6: Pipes and Cisterns (including Leak/Outlet problems)
  11. Type 7: Work Equivalence (Man-Days-Hours) Method
  12. Common Shortcuts and Tricks
  13. Common Mistakes to Avoid
  14. Solved Examples (25 fully worked problems)
  15. Practice Question Bank (50 questions)
  16. Answer Key with Quick Solutions

1. Introduction to the Topic

Time and Work is one of the highest-yield chapters in the Quantitative Aptitude section of every major competitive exam — SSC CGL, CHSL, MTS, CPO, RRB NTPC, Group D, JE, banking exams, and state-level recruitment tests. On average, exams set 2–4 questions directly from this chapter, and the underlying “efficiency” logic reappears inside Pipes and Cisterns, Work and Wages, and even some Time-Speed-Distance hybrid questions.

The entire chapter rests on one idea: work is directly proportional to the number of workers and the time they work, and inversely proportional to the time taken when the number of workers increases. Once a candidate internalizes this proportionality and the LCM (total work) shortcut, 90% of Time and Work questions can be solved in under 45 seconds.

This guide builds from the ground up: definitions, formulas, the LCM method, every major question pattern seen in the last ten years of papers, fully worked examples, and a large practice bank with solutions.


2. Basic Concepts and Terminology

Work: An abstract task assumed to have a fixed, measurable quantity, usually treated as “1 unit” of work (e.g., “build a wall,” “fill a tank,” “type a manuscript”).

Time: The duration taken to complete the work, usually in days, hours, or minutes.

Efficiency (Rate of Work): The amount of work a person/machine can do in one unit of time. If a person completes a job in n days, their efficiency is 1/n of the work per day.

Man-Days: A unit representing the amount of work one person can do in one day. If a job takes 10 men 6 days, the job requires 60 man-days of work.

Direct and Inverse Proportion in this chapter: - Work ∝ Number of workers (more workers → more work done in same time) — direct - Work ∝ Time (more time → more work done) — direct - Time ∝ 1/Number of workers (more workers → less time needed) — inverse - Efficiency ∝ 1/Time taken (faster completion → higher efficiency) — inverse

These four relationships are the backbone of every formula in this chapter.


3. Core Formulas

Formula 1 — Basic Work Rate If A can complete a work in n days, then: - A’s one day’s work = 1/n - If A’s one day’s work = 1/n, then A can finish the work in n days.

Formula 2 — Combined Work If A can do a work in a days and B can do it in b days, working together they finish it in:

Time together = (a × b) / (a + b) days

Formula 3 — Three or More Workers If A, B, and C can individually complete work in a, b, c days:

Combined 1 day’s work = 1/a + 1/b + 1/c Time together = 1 / (1/a + 1/b + 1/c)

Formula 4 — Efficiency Ratio If A is k times as efficient as B, then A takes 1/k times the time B takes. Efficiency ratio A : B = Time ratio B : A (inverse relationship)

Formula 5 — Work Done in Given Time Work done by A in t days = t/n (where n = total days A needs alone)

Formula 6 — Remaining Work Remaining work = 1 − (work already completed)

Formula 7 — Wages Distribution Wages are distributed in the ratio of work done, which (for the same time period) equals the ratio of efficiencies. Wage ratio = Efficiency ratio (when time worked is equal)

Formula 8 — Pipes and Cisterns (Filling/Emptying) - Inlet pipe fills tank in x hours → rate = +1/x per hour - Outlet pipe empties tank in y hours → rate = −1/y per hour - Combined rate = sum of individual signed rates - Time to fill/empty = 1 / (combined rate)

Formula 9 — Man-Day-Hour Equation (Work Equivalence)

(M₁ × D₁ × H₁) / W₁ = (M₂ × D₂ × H₂) / W₂

Where M = men, D = days, H = hours/day, W = amount of work (use W = 1 if it’s the same job, or actual quantities like “walls built” if different jobs).


4. The LCM (Total Work) Method — The Master Technique

Figure: LCM method turns fractions into whole-number efficiencies.

This is the single most important technique in this chapter and should replace fraction-heavy algebra in almost every problem.

Steps: 1. Take the LCM of all the individual times given in the question. Call this the “Total Work” (in units). 2. Divide Total Work by each person’s individual time to get their efficiency (units of work per day). 3. Now the entire problem becomes simple arithmetic with whole numbers — no fractions.

Example: A can do a job in 12 days, B in 8 days. - LCM of 12 and 8 = 24 → Total Work = 24 units. - A’s efficiency = 24/12 = 2 units/day - B’s efficiency = 24/8 = 3 units/day - Combined efficiency = 5 units/day - Time together = Total Work / Combined efficiency = 24/5 = 4.8 days

This matches the fraction method exactly but avoids fraction addition, which is where most calculation errors and time loss happen under exam pressure. Every solved example in this guide uses this method as the primary approach, with the formula method shown alongside for verification.


5. Type 1: Individual Efficiency Problems

These give you individual times and ask for combined time, or vice versa.

Pattern: “A can do a piece of work in x days and B in y days. In how many days can they finish it together?”

Approach: LCM method (Section 4) or Formula 2.

Reverse pattern: “A and B together can finish a work in x days. A alone can finish it in y days. Find B’s time alone.” - Total work = LCM(x, y) or any common multiple - Combined efficiency = Total work / x - A’s efficiency = Total work / y - B’s efficiency = Combined − A’s efficiency - B’s time = Total work / B’s efficiency


6. Type 2: Two or More Persons Working Together

Extends Type 1 to three or more workers, sometimes with some working only part of the time.

Pattern: “A, B, and C can complete a work in 10, 15, and 30 days respectively. They all start together, but A leaves after 3 days and B leaves 2 days before the work is finished. In how many days is the work completed?”

Approach: 1. Find total work (LCM of 10, 15, 30 = 30 units) 2. Efficiencies: A = 3, B = 2, C = 1 units/day 3. Let total days = d. B leaves 2 days before finish, so B works (d − 2) days. A works only 3 days. C works all d days. 4. Equation: 3(3) + 2(d − 2) + 1(d) = 30 5. Solve: 9 + 2d − 4 + d = 30 → 3d + 5 = 30 → 3d = 25 → d = 25/3 days


7. Type 3: Work Left / Work Done in Parts (Alternate Days)

Figure: Alternate-day work pattern between two workers.

Pattern: “A and B can do a work in 12 and 18 days respectively. They work on alternate days starting with A. In how many days will the work be completed?”

Approach (LCM method): 1. Total work = LCM(12, 18) = 36 units 2. A’s efficiency = 3 units/day, B’s efficiency = 2 units/day 3. In each pair of days (A’s day + B’s day), work done = 3 + 2 = 5 units 4. Number of complete pairs needed: 36/5 = 7 pairs (14 days) with remainder 1 unit → 35 units done in 14 days 5. Day 15 is A’s turn (since A started): A does 3 units/day, only 1 unit remains → A needs 1/3 of a day 6. Total time = 14 + 1/3 = 14⅓ days

Key tip: Always check who starts and whether the final fractional day is worked by the faster or slower person — this changes the answer.


8. Type 4: Men, Women, Children — Comparative Efficiency

Pattern: “2 men and 3 women can complete a work in 10 days. 4 men and 6 women can complete it in x days. Find x.” OR “If 1 man = 2 women = 3 children in efficiency, and 4 men can build a wall in 12 days, how many days will 6 women and 4 children take?”

Approach: Convert everyone into a single unit (usually “man-equivalent”) using the given efficiency ratio, then apply the man-day-hour formula (Formula 9).

Standard efficiency ratio conversions (when given like “A man does twice the work of a woman, and a woman does twice the work of a child”): - 1 man = 2 women = 4 children (in efficiency)


9. Type 5: Work and Wages

Core rule: Wages are always divided in the ratio of work contributed, not in the ratio of efficiency alone — this matters when people work different numbers of days.

Wage share ratio = (Efficiency × Days worked) ratio = (Work done) ratio

Pattern: “A can do a work in 6 days, B in 8 days. They complete the work together and are paid ₹840. Find each one’s share.”

Approach: 1. Total work = LCM(6,8) = 24 units. A’s efficiency = 4, B’s efficiency = 3. 2. Since they work together for the same duration, wage ratio = efficiency ratio = 4:3 3. A’s share = 840 × 4/7 = ₹480; B’s share = 840 × 3/7 = ₹360

Trickier version: “A, B, and C undertake a work for ₹1200. A and B together are supposed to do 5/7 of the work. How much does C get?” - C’s share of work = 1 − 5/7 = 2/7 - C’s payment = 1200 × 2/7 = ₹342.86 (or as a fraction, 2400/7)


10. Type 6: Pipes and Cisterns (including Leak/Outlet problems)

Figure: Inlet pipes add to the tank (+), outlet pipes subtract (−).

Pipes and Cisterns is structurally identical to Time and Work, with “filling a tank” replacing “completing work,” and outlet pipes/leaks acting as negative work (they undo completed work).

Pattern A — Fill and empty together: “Pipe A fills a tank in 6 hours. Pipe B empties it in 9 hours. If both are opened together, how long to fill the tank?” - LCM(6,9) = 18 units (tank capacity) - A’s rate = +3 units/hr, B’s rate = −2 units/hr - Net rate = +1 unit/hr - Time to fill = 18/1 = 18 hours

Pattern B — Leak in a filled tank: “A pipe can fill a tank in 12 hours. Due to a leak, it takes 16 hours to fill. In how long will the leak alone empty a full tank?” - LCM(12,16) = 48 units - Pipe’s rate = +4 units/hr; with leak, net rate = 48/16 = 3 units/hr - Leak’s rate = 4 − 3 = 1 unit/hr (emptying) - Leak alone empties the tank in 48/1 = 48 hours

Pattern C — Pipe opened for part of the time (alternate pipes): Similar to Type 3 (alternate days), just replace “work” with “tank capacity.”

Special note — Cistern with two inlets, opened at different times: “Pipe A alone can fill in 12 hrs, Pipe B alone in 15 hrs. Both are opened together but B is closed 3 hours before the tank is full. Find total time.” - LCM(12,15) = 60 units. A = 5/hr, B = 4/hr. - Let total time = t hrs. B works (t−3) hrs, A works t hrs. - 5t + 4(t−3) = 60 → 5t + 4t − 12 = 60 → 9t = 72 → t = 8 hours


11. Type 7: Work Equivalence (Man-Days-Hours) Method

Used for problems that compare two different scenarios of workers/days/hours to a different quantity of work (e.g., “walls,” “km of road,” “copies of a book”).

Formula: (M₁D₁H₁)/W₁ = (M₂D₂H₂)/W₂

Pattern: “12 men working 8 hours a day can complete a piece of work in 10 days. How many days will 15 men working 6 hours a day take to complete the same work?” - (12 × 8 × 10)/1 = (15 × 6 × D)/1 - 960 = 90D → D = 10.67 days

Pattern with different work quantities: “20 men can build a 56 m long wall in 6 days. How many men are required to build a 42 m wall in 3 days?” - (M₁D₁)/W₁ = (M₂D₂)/W₂ - (20×6)/56 = (M₂×3)/42 - 120/56 = 3M₂/42 → M₂ = (120×42)/(56×3) = 30 men


12. Common Shortcuts and Tricks

  1. Always convert to the LCM method — it eliminates fraction arithmetic and is far faster under time pressure.
  2. “A is k times as good as B” ⇒ Efficiency A : B = k : 1 ⇒ Time A : B = 1 : k. Do not confuse efficiency ratio with time ratio — they are inverses of each other.
  3. When three people work and one is a “spoiler” (works against, like a leak or a person who spoils work), treat their contribution as negative in the efficiency sum.
  4. For “A and B together” vs “A and B on alternate days”, remember alternate-day problems almost always need the day-by-day cycle checked near the end (the last fractional day matters).
  5. Wages ratio = work-done ratio, not time-worked ratio, unless efficiencies are equal.
  6. When a problem gives “twice as efficient,” “thrice as fast,” “takes half the time”, immediately convert this into a numeric efficiency or time ratio before doing anything else.
  7. Percentage-based work problems (“A can do 20% of the work in a day”) are just efficiency stated as a percentage — 20% per day means the person finishes in 100/20 = 5 days.
  8. Pipes and cisterns with negative pipes (leaks): always find the net rate; never add magnitudes blindly — subtract the outlet’s rate.
  9. When multiple people join or leave at different points, always express things in terms of “total units of work” completed till each event, and use one clean equation for the unknown time/day.
  10. Practice recognizing that Time and Work, Pipes and Cisterns, and Work and Wages are the same skeleton wearing different clothing — master one, master all three.

13. Common Mistakes to Avoid

  • Adding times instead of efficiencies: A takes 4 days, B takes 6 days — the combined time is NOT (4+6)/2 = 5 days. It is (4×6)/(4+6) = 2.4 days.
  • Confusing “twice as efficient” with “twice the time”: twice as efficient means HALF the time, not double.
  • Forgetting to subtract leak/outlet rates in pipes and cisterns problems.
  • Ignoring partial last-day work in alternate-day problems — a common trap where students round instead of computing the exact fraction of the last working day.
  • Using time-worked ratio instead of work-done ratio for wage distribution when efficiencies differ.
  • Sign errors when a pipe empties a “partially filled” tank versus a “full” tank — always define what fraction is already present before applying rates.
  • Not converting hours/days consistently — mixing “days” and “hours” without converting is a very common cause of wrong answers in Man-Day-Hour formula questions.

14. Solved Examples (25 Fully Worked Problems)

Example 1. A can complete a work in 15 days and B in 10 days. In how many days will they finish it together? Solution: LCM(15,10) = 30 units. A’s efficiency = 2, B’s efficiency = 3. Combined = 5 units/day. Time = 30/5 = 6 days.

Example 2. A and B together can complete a work in 12 days. A alone can do it in 20 days. In how many days can B alone complete it? Solution: Total work = LCM(12,20) = 60 units. Combined efficiency = 60/12 = 5. A’s efficiency = 60/20 = 3. B’s efficiency = 5−3 = 2. B’s time = 60/2 = 30 days.

Example 3. A is twice as efficient as B. If B can complete a work in 24 days, in how many days will A and B together complete it? Solution: B’s efficiency = 1 unit/day (in a scale where total work = 24). A’s efficiency = 2 units/day. Combined = 3 units/day. Time = 24/3 = 8 days.

Example 4. 15 men can complete a work in 20 days. In how many days will 25 men complete the same work? Solution: Total man-days = 15×20 = 300. Days for 25 men = 300/25 = 12 days.

Example 5. A can do a work in 18 days. He worked for 6 days and left. B finished the remaining work in 24 days. In how many days can B alone complete the whole work? Solution: Total work = 18 units (taking A’s time as base for simplicity, efficiency of A =1). A did 6 units in 6 days. Remaining = 12 units, done by B in 24 days ⇒ B’s efficiency = 12/24 = 0.5 units/day ⇒ B’s time for 18 units = 18/0.5 = 36 days.

Example 6. A, B, and C can complete a work in 10, 12, and 15 days respectively. They all work together. Find the time taken and each one’s share of work if total payment is ₹740. Solution: LCM(10,12,15) = 60. Efficiencies: A=6, B=5, C=4. Combined = 15 units/day. Time = 60/15 = 4 days. Wage ratio 6:5:4 (total 15 parts). A = 740×6/15 = ₹296; B = 740×5/15 ≈ ₹246.67; C = 740×4/15 ≈ ₹197.33.

Example 7. A and B can complete a work in 12 days working together. They worked together for 3 days, then A left. B finished the remaining work in 18 more days. Find A’s and B’s individual times. Solution: Combined efficiency (scale total work = 36, LCM(12, ?) — let’s just use total work = 36 based on combined rate 3/day since 36/12=3). In 3 days together: 9 units done. Remaining 27 units done by B alone in 18 days ⇒ B’s efficiency = 27/18 = 1.5 units/day ⇒ B’s time = 36/1.5 = 24 days. A’s efficiency = combined − B = 3 − 1.5 = 1.5…

Let’s redo with cleaner total work. Combined rate = Total/12. Let total work = 36 (multiple of 12). Combined efficiency = 3/day. In 3 days: 9 units done, 27 remain. B does 27 units in 18 days ⇒ B efficiency = 1.5/day ⇒ B’s time alone = 36/1.5 = 24 days. A’s efficiency = 3 − 1.5 = 1.5/day ⇒ A’s time alone = 36/1.5 = 24 days. (Interesting — both take 24 days, verifiable since combined of two people each taking 24 days: (24×24)/48=12 ✓ matches given.)

Example 8. A tap can fill a tank in 8 hours. Another tap can empty it in 12 hours. If both taps are opened simultaneously, in how many hours will the tank be full? Solution: LCM(8,12)=24. Fill rate = 3/hr, empty rate = 2/hr. Net = 1/hr. Time = 24/1 = 24 hours.

Example 9. Two pipes A and B can fill a tank in 20 and 30 minutes respectively. Both are opened together, but after 5 minutes, pipe A is closed. In how many more minutes will the tank be filled by pipe B alone? Solution: LCM(20,30)=60 units. A=3/min, B=2/min. In 5 min together: (3+2)×5=25 units. Remaining=35 units. B fills 35 units at 2/min = 17.5 minutes more.

Example 10. A can do a piece of work in 24 days. If B is 60% more efficient than A, in how many days can B alone do the work? Solution: B’s efficiency = 1.6 × A’s efficiency. Time is inversely proportional: B’s time = 24/1.6 = 15 days.

Example 11. 4 men and 6 women can complete a work in 8 days. 3 men and 7 women can complete the same work in 10 days. In how many days will 10 women complete it alone? Solution: Let 1 man = m units/day, 1 woman = w units/day. (4m+6w)×8 = (3m+7w)×10 32m + 48w = 30m + 70w 2m = 22w → m = 11w Total work = (4m+6w)×8 = (44w+6w)×8 = 50w×8 = 400w 10 women’s efficiency = 10w. Time = 400w/10w = 40 days.

Example 12. A can finish a work in 20 days and B in 25 days. They started working together, but 3 days before the work finished, A left. In how many total days was the work completed? Solution: LCM(20,25)=100. A=5/day, B=4/day. Let total days = d. A worked (d−3) days, B worked d days. 5(d−3) + 4d = 100 → 5d −15 +4d = 100 → 9d = 115 → d = 12.78 days (≈12 8/9 days). So d ≈ 12.78 days.

Example 13. A can copy 75 pages in 25 hours. A and B together can copy 135 pages in 27 hours. In how many hours can B copy 42 pages? Solution: A’s rate = 75/25 = 3 pages/hr. Combined rate = 135/27 = 5 pages/hr. B’s rate = 5−3 = 2 pages/hr. Time for 42 pages = 42/2 = 21 hours.

Example 14. A, B, and C can do a work in 6, 8, and 12 days respectively. They start together, but C leaves 2 days before completion. In how many days is the work completed? Solution: LCM(6,8,12)=24. A=4, B=3, C=2/day. Let total days=d. C works (d−2) days; A, B work d days each. 4d + 3d + 2(d−2) = 24 → 9d − 4 = 24 → 9d = 28 → d = 28/9 ≈ 3.11 days.

Example 15. 8 men can complete a job in 15 days. After 5 days, 4 more men join. In how many total days will the work finish? Solution: Total work = 8×15 = 120 man-days. In 5 days, 8 men do 40 man-days; remaining = 80 man-days. Now 12 men work: 80/12 = 6.67 days more. Total = 5 + 6.67 ≈ 11.67 days.

Example 16. A can do a work in 40 days. He works at it for 8 days and then B finishes the remaining work in 16 days. In how many days will A and B together finish the whole work? Solution: Total work=40 units (A’s efficiency=1/day). A did 8 units in 8 days; remaining 32 units done by B in 16 days ⇒ B’s efficiency=2/day. Combined efficiency=1+2=3/day. Time=40/3 ≈ 13.33 days.

Example 17. A leak in the bottom of a tank can empty a full tank in 6 hours. An inlet pipe fills water at 4 litres/minute. When the tank is full, the inlet is opened and due to the leak, the tank empties in 8 hours. Find the capacity of the tank. Solution: Let capacity = C litres. Leak’s rate = C/6 per hour (emptying). Inlet’s rate = 4×60=240 L/hr (filling). Net emptying rate with both = C/8 per hour. C/6 − 240 = C/8 C/6 − C/8 = 240 (4C − 3C)/24 = 240 → C/24 = 240 → C = 5760 litres.

Example 18. A and B undertake to do a piece of work for ₹600. A alone can do it in 6 days, B alone in 8 days. With the help of C they finish it in 3 days. Find C’s share. Solution: LCM(6,8,3)=24. A=4/day, B=3/day. Combined (A+B+C) = 24/3 = 8/day. C’s efficiency = 8−4−3=1/day. Total efficiency=8, C’s share=600×1/8=₹75.

Example 19. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, find the time taken by 15 men and 20 boys to do the same work. Solution: (6m+8b)10 = (26m+48b)2 60m+80b = 52m+96b 8m = 16b → m=2b Total work = 60m+80b = 60(2b)+80b=200b 15 men+20 boys efficiency=15(2b)+20b=30b+20b=50b Time=200b/50b=4 days.

Example 20. A alone can do a work in 6 days and B alone in 8 days. A and B undertake to do it for ₹3200 and completed it with the help of C in 3 days. What is C’s share? (Same structure as Example 18, different numbers) LCM(6,8,3)=24. A=4/day, B=3/day, combined all three=24/3=8/day. C=8−4−3=1/day. C’s share=3200×(1/8)=₹400.

Example 21. Two typists undertake to do a job. The first typist can complete the job alone in 6 hours while the second in 8 hours. After working alone for 1 hour, the first typist is joined by the second. In how many hours from the start is the job completed? Solution: LCM(6,8)=24. First=4/hr, second=3/hr. In first hour alone: 4 units done. Remaining=20 units. Together they do 4+3=7/hr. Time=20/7 hours more. Total = 1 + 20/7 = 27/7 ≈ 3.86 hours.

Example 22. A can do 1/4 of a work in 3 days. B can do 2/5 of the same work in 4 days. In how many days can both together complete the work? Solution: A’s full time = 3×4 = 12 days (since 1/4 done in 3 days). B’s full time = 4×(5/2) = 10 days. LCM(12,10)=60. A=5, B=6/day. Combined=11/day. Time=60/11 ≈ 5.45 days.

Example 23. 45 men can complete a work in 16 days. Six days after they started, 30 more men joined them. How many days will they now take to complete the remaining work? Solution: Total work = 45×16=720 man-days. In 6 days, 45 men do 270 man-days. Remaining=450 man-days. Now 75 men work: 450/75=6 more days.

Example 24. A tank has two inlet pipes and one outlet pipe. Inlet A fills in 12 hrs, inlet B fills in 15 hrs, outlet C empties in 20 hrs. If all three are opened together, how long to fill the tank? Solution: LCM(12,15,20)=60. A=5, B=4 (fill, +), C=3 (empty, −). Net=5+4−3=6/hr. Time=60/6=10 hours.

Example 25. A does half as much work as B in three-fourths of the time taken by B. If together they take 18 days to complete the work, how much time would B alone take? Solution: Let B’s time = x days ⇒ B’s efficiency=1/x. A does half as much work in (3/4)x days, meaning: A’s efficiency × (3/4)x = (1/2) × (B’s total work equivalent, treat work=1 relative unit done by B in x days so B’s rate =1/x per day; “half as much work” in that (3/4)x period means A produces amount = (1/2)*(rate needed to be compared)). Standard shortcut result for this classic question: A’s time = (3/2)x… Let’s derive cleanly.

Let total work = 1. B’s rate = 1/x. “A does half as much work as B in 3/4 of the time B takes” → in time (3/4)x, A does work = (1/2) × (work B would do in that same (3/4)x time) = (1/2) × (3/4)x × (1/x) = 3/8. So A’s rate = (3/8) ÷ (3/4)x = (3/8)×(4/(3x)) = 1/(2x). Combined rate = 1/x + 1/(2x) = 3/(2x) Given combined time = 18 days ⇒ 3/(2x) = 1/18 ⇒ x = 27. B alone takes 27 days.


15. Practice Question Bank (50 Questions)

Set A — Basic Efficiency (Q1–Q10) 1. A can do a work in 9 days and B in 18 days. Find the time taken together. 2. A can complete a task in 25 days, B in 20 days. Working together, find the time taken. 3. A and B together can do a work in 6 days. A alone can do it in 9 days. Find B’s time alone. 4. A is thrice as efficient as B and takes 20 days less than B to complete a job. Find the time A takes alone. 5. If 20 men can build a wall in 15 days, how long will 25 men take? 6. A can do a work in 15 days. B is 50% more efficient than A. Find B’s time alone. 7. A, B, and C can do a work in 20, 30, and 60 days respectively. Find the time taken together. 8. A works twice as fast as B. If both together can complete a work in 12 days, find A’s individual time. 9. 12 men can complete a work in 18 days. How many men are needed to complete it in 8 days? 10. A can finish a work in 18 days, and B in 15 days. If they work on alternate days starting with B, in how many days will the work finish?

Set B — Joining/Leaving Problems (Q11–Q20) 11. A and B can do a work in 12 and 15 days respectively. They work together for 4 days, then A leaves. In how many more days will B finish the remaining work? 12. A can do a work in 20 days. He works for 4 days and leaves. B finishes the rest in 24 days. Find B’s total time alone. 13. A, B, and C together can complete a work in 6 days. A alone can do it in 18 days, B alone in 24 days. Find C’s time alone. 14. 10 men can complete a work in 12 days. After 4 days, 5 men leave. In how many more days will the remaining work be completed? 15. A and B can do a piece of work in 30 days. They worked together for 20 days and then B left. A finished the remaining work in 20 more days. Find A’s individual time. 16. Twenty women can do a work in 16 days. Sixteen men can do the same work in 15 days. What is the ratio of the daily work done by a man to that of a woman? 17. A can do a job in 40 days. He works for 10 days and then B, who is thrice as efficient as A, joins him. In how many more days will the work be completed? 18. A, B, and C can complete a work in 24, 36, and 48 days. All three start together, and A leaves after 4 days, B leaves 6 days before completion. Find the total days taken. 19. 45 men can complete a work in 20 days working 8 hours a day. In how many days can 30 men complete the same work working 10 hours a day? 20. A does a work in 24 days. B does the same work in 32 days. They start together, but A leaves 4 days before completion. Find total days taken.

Set C — Pipes and Cisterns (Q21–Q32) 21. Pipe A fills a tank in 10 hours, pipe B in 15 hours. Both opened together, find the time to fill. 22. A pipe fills a tank in 6 hours. Due to a leak, it takes 8 hours. Find the time the leak alone would take to empty the full tank. 23. Two pipes can fill a cistern in 14 and 16 hours respectively. The pipes are opened simultaneously, and it is found that due to leakage, 32 minutes extra are taken for the cistern to be filled. If the cistern is full, in what time would the leak empty it? 24. Pipe A can fill a tank in 20 minutes, pipe B can empty it in 30 minutes. If both pipes are opened together when the tank is empty, in how much time will it be full? 25. Three pipes A, B, C can fill a tank in 12, 15, and 20 hours respectively. All are opened together; find the time to fill. 26. A cistern has a leak that would empty it in 20 hours. A tap is turned on which admits 4 litres a minute, and now the cistern is emptied in 40 hours. Find the capacity of the cistern. 27. Two pipes can fill a tank in 12 and 18 minutes. If both pipes are opened simultaneously, after how much time should the first pipe be turned off so that the tank is full in 10 minutes? 28. A tank is filled by pipe A in 8 hours. Because of a leak, it took 2 more hours to fill. Find how long the leak takes to empty the full tank. 29. Two taps can separately fill a cistern in 10 and 15 minutes and when the waste pipe is open, they can together fill it in 18 minutes. Find how long the waste pipe takes to empty the full cistern. 30. Pipe A can fill a tank in 30 minutes. Pipe B can fill it in 45 minutes. Pipe C can empty the full tank in 60 minutes. If all three pipes are opened at the same time, in how much time will the tank be full? 31. A tank has two outlet pipes. Pipe A alone empties it in 24 minutes, pipe B alone in 32 minutes. If both are opened together on a full tank, in how much time will the tank be empty? 32. A pipe can fill a tank in 4 hours. Due to a leak in the bottom, it takes 5 hours to fill the tank. If the tank is full, how much time will the leak take to empty it?

Set D — Work and Wages (Q33–Q38) 33. A and B can do a work in 12 and 18 days. They complete the work together and receive ₹900 total. Find each share. 34. A, B, and C together earn ₹2400 for a work. A can do it alone in 6 days, B in 8, C in 12. Find C’s share. 35. A does 3/4 of a work in 12 days, then B finishes the remaining work in 3 days. If total wages are ₹1500, find A’s and B’s shares. 36. Three workers A, B, and C can complete a task in 15, 20, and 30 days respectively. If total payment is ₹1300, find the wage of B. 37. A can lay bricks twice as fast as B. Working together they earn ₹450 for a job. Find A’s share. 38. A and B undertake a work for ₹720. With C’s help they finish in 3 days instead of the 6 days A and B alone would take. Find C’s share.

Set E — Man-Day-Hour Equivalence (Q39–Q45) 39. 16 men working 8 hours a day can complete a work in 10 days. In how many days will 20 men working 10 hours a day complete the same work? 40. 25 men can reap a field in 20 days. How many men are needed to reap it in 10 days? 41. If 6 men and 4 women can complete a work in 10 days, and 3 men and 7 women can do the same in 12 days, find how long 10 women alone would take. 42. 20 men can build a wall 100 m long in 15 days. In how many days can 25 men build a wall 150 m long? 43. A contractor employed 60 men to complete a work in 20 days. After 10 days, he found only 40% of the work was done. How many more men must be employed to finish on time? 44. 12 men and 16 women can complete a piece of work in 5 days. 13 men and 24 women can complete the same work in 4 days. In how many days will 7 men and 10 women complete it? 45. 10 women can complete a work in 8 days, and 10 children take 12 days to complete it. How many days will 5 women and 10 children take to complete the work?

Set F — Mixed / Advanced (Q46–Q50) 46. A can do a work in x days and B in (x+8) days. Together they can do it in 6 days. Find x. 47. A, B, and C can complete a work in 6, 12, and 24 days respectively. They all start together. After 2 days, C leaves; after 2 more days, B leaves. In how many total days is the work completed? 48. A alone would take 8 hours more to complete a job than if both A and B worked together. If B, working alone, would take 4.5 hours more than A and B together, find the time A and B would take together. 49. Two workers A and B are engaged to do a piece of work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 4.5 hours more than the time needed if both worked together. What time would they take if both worked together? 50. A man, a woman, and a boy can together complete a piece of work in 3 days. A man alone can do it in 6 days and a boy alone in 18 days. How long will a woman alone take to complete the work?


16. Answer Key with Quick Solutions

Set A 1. LCM(9,18)=18; eff 2+1=3; 6 days 2. LCM(25,20)=100; eff 4+5=9; 100/9 ≈ 11.11 days 3. LCM(6,9)=18; comb=3, A=2, B=1; B=18 days 4. Let B=t, A=t/3. t−t/3=20 ⇒ (2t/3)=20 ⇒ t=30; A=10 days 5. 20×15=25×d ⇒ d=12 days 6. B’s time=15/1.5=10 days 7. LCM=60; eff 3+2+1=6; 10 days 8. B=t, A=t/2; comb eff: total work=t; 1/t+2/t=1/12⇒3/t=1/12⇒t=36; A=18 days 9. 12×18=216 man-days; 216/8=27 men 10. LCM(18,15)=90; B(day1)=6,A(day2)=5; pair=11/2days→units. After 8 pairs(16 days):8×11=88, remaining=2, day17 is B’s turn(6/day) needs 2/6=1/3 day; Total=16+1/3=16⅓ days 11. LCM(12,15)=60;A=5,B=4;4days together=36;remain24;B alone:24/4=6 more days 12. Total=20;A did4;remain16 in24days⇒B eff=16/24=2/3;B time=20/(2/3)=30 days 13. LCM(18,24,6)=72;A=4,B=3;comb=72/6=12;C=12−4−3=5;C time=72/5=14.4 days 14. Total=120man-days;4days×10=40;remain80;5men left→5 men work:80/5=16 more days 15. Total=30x scale: let total work=30(LCM placeholder), combined eff=1(since 30days);Actually solve directly: combined rate=1/30/day. 20 days together=20/30=2/3 done;remainder1/3 by A in20days⇒A rate=1/60/day⇒A alone=60 days 16. 20w×16=16m×15⇒320w=240m⇒m/w=320/240=4:3 17. Total=40;A eff=1;B eff=3;10days alone=10 units done by A;remain30;combined(A+B)=4/day;30/4=7.5;Total=10+7.5=17.5 days 18. LCM(24,36,48)=144;A=6,B=4,C=3;let total=d;A works4days,B works(d−6),C works d: 6(4)+4(d−6)+3d=144⇒24+4d−24+3d=144⇒7d=144⇒d≈20.57 days 19. 45×20×8=30×D×10⇒7200=300D⇒D=24 days 20. LCM(24,32)=96;A=4,B=3;let d=total;A works(d−4);B works d:4(d−4)+3d=96⇒4d−16+3d=96⇒7d=112⇒d=16 days

Set C 21. LCM(10,15)=30;A=3,B=2;comb5;6 hours 22. LCM(6,8)=24;pipe=4,net w/leak=3;leak=1;time=24/1=24 hours 23. LCM(14,16)=112;A=8,B=7,comb=15;without leak time=112/15 hr;with leak time=112/15+32/60 hr; find leak’s net rate then isolate leak time — standard answer: 112 hours (classic result equals product form; compute: t=112/15+8/15=120/15=8hr with leak; net rate=112/8=14; leak=15−14=1; leak time=112/1=112 hours) 24. LCM(20,30)=60;A=3,B=2;net=1;60 minutes 25. LCM(12,15,20)=60;A=5,B=4,C=3;comb=12;5 hours 26. Leak rate=C/20 per hr;with tap:net empty=C/40;C/20−(4×60)=C/40⇒C/20−C/40=240⇒C/40=240⇒C=9600 litres 27. Let first pipe open for t min, both together give: t(1/12+1/18)+(10−t)(1/18)=1. LCM(12,18)=36:eff A=3,B=2. t(5)+(10−t)(2)=36⇒5t+20−2t=36⇒3t=16⇒t=16/3≈5.33 minutes 28. LCM base: pipe fills in8hr(eff x),with leak 10hr. Let total=40(LCM 8,10);pipe=5,net=4;leak=1;leak time=40/1=40 hours 29. LCM(10,15,18)=90;A=9,B=6,comb without waste=15;with waste net=90/18=5;waste=15−5=10;waste time=90/10=9 minutes 30. LCM(30,45,60)=180;A=6,B=4,C=−3;net=7;180/7≈25.7 minutes 31. LCM(24,32)=96;A=4,B=3;comb=7;96/7≈13.7 minutes 32. LCM(4,5)=20;pipe=5,net=4;leak=1;20 hours

Set D 33. LCM(12,18)=36;A=3,B=2;ratio3:2;A=900×3/5=₹540,B=₹360 34. LCM(6,8,12)=24;A=4,B=3,C=2;total9;C=2400×2/9≈₹533.33 35. A’s rate info gives A’s total time=16days(3/4 in12⇒full=16);B’s:did1/4 in3days⇒full=12days. LCM(16,12)=48;A=3,B=4/day.A worked12days=36units,B worked3days=12units;total=48✓.ratio A:B=36:12=3:1;A=1500×3/4=₹1125,B=₹375 36. LCM(15,20,30)=60;A=4,B=3,C=2;total9;B=1300×3/9≈₹433.33 37. Ratio2:1;A=450×2/3=₹300 38. A+B time=6days(combined,from”A and B alone would take6days”basis-implied);with C=3days. Let total work=LCM(6,3)=6;A+B eff=1;with C eff=2;C=2−1=1;C share=720×1/2=₹360 39. 16×8×10=20×10×D⇒1280=200D⇒D=6.4 days 40. 25×20=D×10⇒D=50 men 41. (6m+4w)10=(3m+7w)12⇒60m+40w=36m+84w⇒24m=44w⇒m=11w/6.Total=60m+40w=60(11w/6)+40w=110w+40w=150w.10 women eff=10w;time=150w/10w=15 days 42. (20×15)/100=(25×D)/150⇒3=25D/150⇒25D=450⇒D=18 days 43. In10days60men did40%⇒rate=4%/day for60men⇒per man=4/60%/day.Remaining60%must be done in10days⇒needed rate=6%/day⇒men needed=6/(4/60)=90men⇒30 more men 44. (12m+16w)5=(13m+24w)4⇒60m+80w=52m+96w⇒8m=16w⇒m=2w.Total=60m+80w=60(2w)+80w=200w.7m+10w eff=7(2w)+10w=24w;time=200w/24w=25/3≈8.33 days 45. 10 women:8days⇒women eff total=1/8/day per “job”, so 1 woman=1/80/day.10 children:12days⇒1 child=1/120/day.5 women+10children eff=5/80+10/120=1/16+1/12=(3+4)/48=7/48;time=48/7≈6.86 days

Set F 46. 1/x+1/(x+8)=1/6 ⇒ 6(x+8)+6x=x(x+8) ⇒6x+48+6x=x²+8x⇒12x+48=x²+8x⇒x²−4x−48=0⇒(x−12)(x+4)=0⇒x=12 days 47. LCM(6,12,24)=24;A=4,B=2,C=1.First2days all three:2(4+2+1)=14.Next2days A&B:2(4+2)=12→total26>24,so finishes before that. After first2days:14 done,remain10.Next with A+B(6/day):10/6=1.67days<2days,so C’s leaving point irrelevant beyond this. Total=2+1.67≈3.67 days 48. Let combined time=T.A=T+8,B=T+4.5.1/(T+8)+1/(T+4.5)=1/T.Solve: this is the classic problem giving T²=8×4.5=36⇒T=6 hours 49. Same as Q48 structure: T=6 hours 50. Man+Woman+Boy=3days⇒comb eff=1/3(scale total=1).Man=1/6,Boy=1/18.Woman=1/3−1/6−1/18=(6−3−1)/18=2/18=1/9⇒Woman alone=9 days



17. Advanced Level (SSC CGL Tier-2 / RRB JE / Toughest Competitive Level)

This section pushes beyond the standard patterns above into the harder, multi-layered variants that appear in SSC CGL Tier-2, RRB JE/SSE, and the toughest state PSC-style papers. These questions typically combine two or more question types (e.g., efficiency ratios + wages + pipes), involve non-integer/algebraic setups, or require setting up and solving an equation rather than direct substitution.

17.1 Advanced Concepts

Work depreciation / variable efficiency: Some advanced questions have a person’s efficiency change over time (e.g., “on day n, a worker’s output falls by 10% of the previous day’s output” — a geometric progression of work done). Total work becomes a GP sum rather than a simple linear count.

Negative work / spoiling work combined with wages: A “spoiler” (child, saboteur, or a partially-broken machine) undoes completed work at a fixed rate; combined with a wage-sharing question, this requires computing net contribution (which can be negative) before allocating payment — and a spoiler’s wage share can be zero or the spoiler may even owe a penalty in some framings (ignore penalty framing unless explicitly asked).

Work equivalence with mixed units (men, women, children, machines): Tier-2 style questions frequently give three or four types of workers together with cross-ratios (e.g., “2 men = 3 women”, “4 women = 5 children”) requiring you to convert everyone to a single “unit worker” before applying the man-day-hour formula.

Simultaneous unknowns: Two unknowns (e.g., both A’s and B’s individual times) determined from two different combined-work scenarios — requires solving simultaneous equations in 1/a and 1/b rather than reading off values directly.

Work with breaks/non-working days: A person works only on certain days of the week (e.g., “A works only on weekdays, B works only on weekends”) — requires cycle-based accounting similar to alternate-day problems but with irregular periods (a 7-day cycle instead of a 2-day cycle).

17.2 Advanced Solved Examples

Advanced Example 1. A can do a piece of work in 24 days. B is 50% more efficient than A, and C is 20% less efficient than B. If all three work together, but C works only every alternate day (starting on day 1), find the total number of days to complete the work. Solution: A’s efficiency=1 unit/day (scale: total work=24). B’s efficiency=1.5. C’s efficiency=1.5×0.8=1.2. On C’s working days: combined=1+1.5+1.2=3.7/day. On C’s off days: combined=1+1.5=2.5/day. Per 2-day cycle: 3.7+2.5=6.2 units. Number of full cycles to approach 24: 24/6.2≈3.87 cycles →3 full cycles (6 days)=18.6 units done. Remaining=5.4 units. Day7 (C works, odd day): rate=3.7/day → time=5.4/3.7≈1.459 days. Total time ≈ 6+1.459 ≈ 7.46 days.

Advanced Example 2. A tank is fitted with 3 inlet pipes and 1 outlet pipe. The inlet pipes can individually fill the tank in 10, 15, and 20 hours; the outlet can empty it in 12 hours. Pipes are opened in order (each new pipe opened 1 hour after the previous), starting with the first inlet, and the outlet pipe is opened last, 3 hours after the first inlet started. Find the time (from the start) at which the tank is full, given tank capacity is 60 units. Solution: Rates: P1=6/hr, P2=4/hr, P3=3/hr, Outlet=−5/hr (LCM=60). Hour1 (0-1): only P1 open → 6 units → total6 Hour2 (1-2): P1+P2=10/hr → 10 units → total16 Hour3 (2-3): P1+P2+P3=13/hr → 13 units → total29 From hour4 onward: all four open, net=6+4+3−5=8/hr. Remaining=60−29=31. Time needed=31/8=3.875 hours. Total time = 3 + 3.875 = 6.875 hours (6 hrs 52.5 min).

Advanced Example 3. A, B, and C together earn ₹5400 for a job. A worked for 6 days, B for 9 days, and C for 4 days. Their daily efficiencies are in the ratio 3:2:5 respectively. Find each person’s share. Solution: Work contribution ratio = efficiency × days: A=3×6=18; B=2×9=18; C=5×4=20. Total=56. A’s share=5400×18/56=₹1735.71; B’s share=₹1735.71; C’s share=5400×20/56=₹1928.57.

Advanced Example 4. A can complete 1/3 of a work in 5 days, working 6 hours a day. B can complete 1/4 of the same work in 6 days, working 5 hours a day. How long will they take to complete the work together, working 8 hours a day? Solution: A’s total man-hours for full work = 5×6×3=90 hours. B’s total man-hours for full work=6×5×4=120 hours. A’s rate=1/90 work/hr; B’s rate=1/120 work/hr. Combined=1/90+1/120=(4+3)/360=7/360 work/hr. Time in hours=360/7≈51.43 hours. At 8 hrs/day: 51.43/8 ≈ 6.43 days.

Advanced Example 5. Twelve men can complete a work in 8 days, working 9 hours a day. After working for 3 days (at 9 hrs/day), the work stopped for 2 days, then resumed with 4 additional men, now working 6 hours a day. In how many more days (at 6 hrs/day) will the work be completed? Solution: Total work=12×8×9=864 man-hours. Work done in first 3 days=12×3×9=324 man-hours. Remaining=540 man-hours. Now 16 men work 6 hrs/day → 96 man-hours/day. Days needed=540/96=5.625 more days.

Advanced Example 6. A can do a work in x days, B in (x+6) days. If together they complete the work in a time such that A does twice as much work as B, find x. Solution: A does twice B’s work in the same time period ⇒ A’s efficiency = 2×B’s efficiency ⇒ 1/x = 2/(x+6) ⇒ x+6=2x ⇒ x=6 days (B takes 12 days).

Advanced Example 7. A cistern has an inlet and outlet. The inlet alone fills it in 4 hours less time than the outlet alone would take to empty it. Together (both open), the tank (initially empty) never fills because the outlet is stronger — instead it takes 12 hours to half-empty a full tank when both are open, starting full. If the inlet fills in x hours and outlet empties in (x+4) hours, find x. Solution: Net rate (emptying, since outlet dominates) = 1/(x+4) − 1/x (this will be negative since outlet is faster; magnitude = 1/x − 1/(x+4)). Half tank empties in 12 hours ⇒ net emptying rate = (1/2)/12 = 1/24. 1/x − 1/(x+4) = 1/24 ⇒ 4/[x(x+4)] = 1/24 ⇒ x(x+4)=96 ⇒ x²+4x−96=0 ⇒ (x+12)(x−8)=0 ⇒ x=8 hours (inlet fills in 8 hrs, outlet empties in 12 hrs).

Advanced Example 8. A, B, and C can do a work in 15, 20, and 30 days respectively. They started the work together. After a few days, A left, and B and C continued. Two days after A left, B also left, and C finished the remaining work alone in 3 more days. Find the total time taken to complete the work. Solution: LCM=60. A=4,B=3,C=2/day. Let A worked for t days (with B,C from day1). Then B+C work for 2 more days after A leaves, then C alone for 3 more days. Work done: t(4+3+2) [while all three work] … actually re-read: “they started together… after a few days A left… two days after A left, B also left… C finished remaining in 3 more days.” So: Phase1 (all three, t days): 9t units. Phase2 (B+C, 2 days): 10 units. Phase3 (C alone,3 days): 6 units. Total: 9t+10+6=60 ↼ 9t=44 ⇒ t=44/9≈4.89 days. Total time = t+2+3 = 44/9+5 = 89/9 ≈ 9.89 days.

Advanced Example 9. A contractor undertakes to complete a road of 360 km in 120 days with 50 workers. After 60 days, only 120 km is completed. Find how many additional workers must be employed to complete the remaining work on time, assuming the same daily efficiency per worker. Solution: Rate so far: 120 km in 60 days with 50 workers ⇒ 120/(60×50)=0.04 km per worker-day. Remaining work=240 km in remaining 60 days. Required worker-days=240/0.04=6000. Workers needed=6000/60=100. Additional workers = 100−50 = 50.

Advanced Example 10. A and B undertake to complete a work for ₹6000. Working together, they can complete it in 8 days. With the help of C, they complete it in 6 days. If C’s share (as paid) is ₹1500, find the ratio of A+B’s combined efficiency to C’s efficiency and verify C’s payment. Solution: A+B combined rate=1/8/day. Let total work=24 (LCM placeholder, scale so A+B rate=3/day, i.e., total=24). With C, combined rate=24/6=4/day ⇒ C’s rate=4−3=1/day. Ratio (A+B):C = 3:1. Total parts=4. C’s share=6000×1/4=₹1500 — matches given, confirming consistency.

17.3 Advanced Practice Question Bank (20 Questions)

  1. A can do a work in 20 days. B is 25% more efficient than A, and C is 20% less efficient than A. All three work together but B works only on odd-numbered days and C only on even-numbered days (A works every day). Find the total time to finish.
  2. A tank has 2 inlets and 2 outlets. Inlets fill in 8 and 12 hours; outlets empty in 16 and 24 hours. All four are opened together, but one outlet (16-hr one) is closed after 4 hours. Find the total time to fill the tank.
  3. A, B, C’s wages are in the ratio of their work done. A worked 5 days, B worked 8 days, C worked 6 days, with efficiencies in ratio 4:3:5. If total payment is ₹4700, find C’s share.
  4. A can complete 2/5 of a job in 6 days working 8 hrs/day. B can complete 3/7 of the same job in 9 days working 6 hrs/day. Find the time (in days, at 8 hrs/day) for both together to complete the job.
  5. 20 workers can build a wall in 15 days working 8 hrs/day. After 5 days, 5 workers leave, and the remaining work is completed by working 10 hrs/day. Find the total number of days taken.
  6. A can do a work in x days, B in (x+5) days. Together they take 6 days. Find x.
  7. An inlet fills a tank in y hours; an outlet empties a full tank in (y+5) hours. Both opened on a full tank empty it (net) in 20 hours. Find y (assume outlet dominates).
  8. A, B, C can complete a work in 12, 15, 20 days. All start together; A leaves after 3 days, B leaves 4 days before completion. Find total days.
  9. A contractor employs 40 men to build a bridge in 100 days. After 40 days, only 30% is done. How many more men are needed to finish on time?
  10. A and B together can complete a work for ₹9000 in 10 days. With C’s help, they finish in 6 days, and C is paid ₹3600. Find A+B’s combined daily efficiency to C’s efficiency ratio.
  11. Twelve men can do a piece of work in 18 days working 6 hrs/day. In how many days can 8 men working 9 hrs/day complete the same work?
  12. A tap fills a tank in 20 minutes. Another tap can fill it 3 times as fast. If both are opened together, find the time to fill the tank.
  13. Two pipes A and B can fill a tank in 24 and 32 minutes. Both opened together; find after how much time B should be closed so the tank fills in exactly 18 minutes total.
  14. A can build a wall in 15 days, B in 20 days, working alone. They work on alternate days, A starting, but every third day (day 3, 6, 9…) both work together instead. Find the total time to complete.
  15. A does 3 times the work of B in 2/3 the time B takes. If together they can complete a work in 15 days, find B’s individual time.
  16. A tank has an inefficient inlet pipe whose rate decreases by 10% each successive hour it runs (first hour it fills at its rated 20 units/hr). Find the total units filled in the first 4 hours.
  17. A, B, and C invested labor in a project. A worked twice as many days as B, and B worked 1.5 times as many days as C. Their daily efficiency ratio is 1:2:3 (A:B:C). If total wage is ₹8800, find each share (in terms of days: let C work d days, B=1.5d, A=3d).
  18. A cistern is filled by pipe A in 6 hours. Pipe B can empty a full cistern in 9 hours. If the cistern is 2/3 full and both pipes are opened together, in how long will it be completely full (or emptied, whichever occurs)?
  19. 15 men and 20 women can complete a work in 8 days. 10 men and 30 women can complete the same work in x days, given 3 men = 5 women in efficiency. Find x.
  20. A can complete a work alone in 30 days. He works alone for 10 days, then is joined by B, and together they complete the remaining work in 8 days. Find B’s individual time alone.

17.4 Advanced Answer Key

  1. A=1,B=1.25,C=0.8/day(scale total=20). Odd days(1,3,5..):A+B=2.25/day. Even days:A+C=1.8/day. Pair(2days)=4.05/day. 20/4.05≈4.94 pairs→4 full pairs(8days)=16.2units. Remaining=3.8. Day9(odd):A+B=2.25/day→3.8/2.25≈1.69days. Total≈8+1.69=9.69 days
  2. LCM(8,12,16,24)=48. Inlets:6+4=10/hr(fill).Outlets:3+2=5/hr(empty,initially both). First4hrs net=10−5=5/hr→20units. After16-hr outlet closes:remaining outlet=2/hr;net=10−2=8/hr.Remaining=48−20=28;time=28/8=3.5hrs.Total=4+3.5=7.5 hours
  3. work ratio=4×5:3×8:5×6=20:24:30=10:12:15;total37;C=4700×15/37≈₹1905.41
  4. A’s full job time=6×8×(5/2)=120hrs(since2/5in6days×8hr=48hrs for2/5,full=48×5/2=120hrs).B’s full=9×6×(7/3)=126hrs.Combined rate=1/120+1/126=(21+20)/2520=41/2520/hr.Time=2520/41≈61.46hrs.At8hr/day:≈7.68 days
  5. first5days@8hr=20×5×8=800man-hrs.Total work=20×15×8=2400.Remaining=1600.Now15workers@10hr/day=150man-hrs/day.Days=1600/150≈10.67.Total≈5+10.67=15.67 days
  6. 1/x+1/(x+5)=1/6⇒6(x+5)+6x=x(x+5)⇒6x+30+6x=x²+5x⇒12x+30=x²+5x⇒x²−7x−30=0⇒(x−10)(x+3)=0⇒x=10 days
  7. 1/y−1/(y+5)=1/20⇒5/[y(y+5)]=1/20⇒y(y+5)=100⇒y²+5y−100=0⇒y=(−5+√425)/2≈8.24 hours
  8. LCM(12,15,20)=60;A=5,B=4,C=3.Let total=d.A works3days,B works(d−4),C works d:5(3)+4(d−4)+3d=60⇒15+4d−16+3d=60⇒7d−1=60⇒7d=61⇒d≈8.71 days
  9. rate=30%of bridge in40days@40men⇒per man-day=0.75%.remaining70%in60days needs rate=70/60=1.1667%/day⇒men=1.1667/0.75×40≈62.2→23 more men (≈62 total, so 22 additional) [precise: men needed=40×(70/60)/(30/40)=40×1.1667/0.75≈62.22→23 additional men (rounding up to 63 total)]
  10. A+B rate=1/10/day(scale total=X).With C:1/6/day.Let total work=30(LCM10,6).A+B=3/day.With C=5/day.C=2/day.Ratio A+B:C=3:2;C’s pay check=9000×? Actually wages should follow this ratio for consistency: total combined work over… this is illustrative;ratio=3:2
  11. 12×18×6=8×D×9⇒1296=72D⇒D=18 days
  12. second tap rate=3×(1/20)=3/20/min;combined=1/20+3/20=4/20=1/5;time=5 minutes
  13. LCM(24,32)=96;A=4,B=3/min.Let B open for t min,A for full18min.18(4)+t(3)=96⇒72+3t=96⇒3t=24⇒t=8 minutes(B open for8min,then closed,A continues alone)
  14. LCM(15,20)=60;A=4,B=3/day.Day1(A alone)=4;Day2(Balone)=3;Day3(both)=7;cycle3days=14units.60/14≈4.29cycles→4cycles(12days)=56units.Remaining=4.Day13(Aalone,pattern repeats):4units exactly.Total=13 days
  15. Let B’s time=x.A does3×work of B in(2/3)x time:A’s rate×(2/3)x=3×[B’s rate×(2/3)x]⇒A’s rate=3×B’s rate=3/x.Combined=1/x+3/x=4/x=1/15⇒x=60 days
  16. rates:20,18,16.2,14.58;sum=20+18+16.2+14.58=68.78 units
  17. days:C=d,B=1.5d,A=3d;work=eff×days:A=1×3d=3d,B=2×1.5d=3d,C=3×d=3d;all equal!ratio1:1:1;each share=8800/3=₹2933.33 each
  18. cistern2/3full(scale total=18,so12unitspresent).A=3/hr(fill),B=2/hr(empty).net=+1/hr.Remaining to fill=6units.Time=6/1=6 hours
  19. 3men=5women⇒1man=5/3women.15men+20women=15(5/3)+20=25+20=45women-equivalent,working8days⇒total work=360woman-days.10men+30women=10(5/3)+30=16.67+30=46.67women-equivalent;x=360/46.67≈7.71 days
  20. total work=30(A’s efficiency=1).A alone10days=10units.remaining=20units in8days by(A+B)⇒combined rate=20/8=2.5/day⇒B’s rate=2.5−1=1.5/day⇒B’s time=30/1.5=20 days

End of Time and Work study material. Continue to the Speed and Distance module for the next high-yield quant chapter, which builds directly on the efficiency/ratio logic learned here.