AMARAVATI, November 6 — The Andhra Pradesh Cabinet, presided over by Chief Minister N. Chandrababu Naidu, formally granted administrative sanction for ₹996 crore dedicated to the construction of a brand-new, full-length Diaphragm Wall (D-Wall) for the Earth-cum-Rockfill (ECRF) dam of the Polavaram Multipurpose Irrigation Project.
The decision brings decisive engineering closure to an impasse regarding damage inflicted on the original sub-surface cutoff wall during the catastrophic Godavari river flood cycles of 2019 and 2020.
Genesis of the Decision: Expert Panel Findings
Technical diagnostics conducted by the Central Water Commission (CWC), Central Soil and Materials Research Station (CSMRS), and international geotechnical consulting consortiums (led by dam specialists from Canada and the United States) confirmed: - Hydrodynamic scour and high-velocity whirlpool scouring caused by incomplete cofferdams had fractured over 35% of the original 1.5-meter-wide plastic concrete cutoff wall. - Attempting localized underwater grouting and stitching would incur excessive uncertainty and risk subterranean piping failure beneath the main ECRF embankment. - The CWC Technical Advisory Committee unanimously recommended sinking an entirely new parallel diaphragm wall 4 to 6 meters upstream of the impaired structure.
Engineering Specifications of the New Diaphragm Wall
- Total Length: 1,396 meters spanning the entire deep Godavari riverbed cross-section between the Left and Right rock abutments. - Maximum Depth: Up to 90 meters below the riverbed level, penetrating coarse sand strata, gravel beds, and anchoring firmly into impervious basal metamorphic bedrock. - Thickness & Material: 1.5-meter-wide plastic concrete formulation engineered with specific bentonite-cement ratios to retain elastomeric flexibility under seismic dynamic loads. - Contract Execution: Awarded to the specialized geotechnical joint venture Bauer Spezialtiefbau and Afcons Infrastructure, utilizing trench cutters and hydraulic grab rigs.
Strategic Timeline Aligned with 2027 Impoundment
The State Water Resources Department mandated continuous round-the-clock drilling and casting during the low-flow fair-weather season, aiming for full structural completion prior to the arrival of the 2027 southwest monsoon. Completion of the cutoff wall is the prerequisite milestone allowing the construction of the 45.72-meter-high main rockfill dam embankment.
Exam Relevance: APPSC Group-1 Mains (GS Paper I — Geography of Andhra Pradesh; Water Resources, River Systems & Major Irrigation Projects; GS Paper III — Infrastructure Financing, Project Delays & Cost Overruns in AP); APPSC Group-2 Prelims & Mains (Polavaram National Project status under AP Reorganisation Act 2014, CWC Clearances); AP State Engineering Services (Civil & Hydraulic Engineering, Geotechnical Foundations); AP Police SI (General Knowledge on State Landmarks). Key facts to remember — Project: Polavaram Diaphragm Wall; Sanctioned cost: ₹996 crore; Approving body: Central Water Commission (CWC) & AP Cabinet; Dimensions: 1,396m length, up to 90m depth, 1.5m thickness; Material: Plastic concrete cutoff wall; River: Godavari (West Godavari / Eluru district); Key objective: Sub-surface seepage prevention for ECRF Dam.