If 18 men can finish a work in 13 days, then in how many days will 54 men finish the same work?
Asked in SSC GD Constable 2024: 20 Feb 2024 Shift 3 · Quantitative Aptitude
Tap an option to check your answer.
Show answer and explanation
Correct answer: (D) 13/3 days
Work = 18×13 = 234 man-days. For 54 men: 234/54 = 13/3 days.
हिंदी में प्रश्न
यदि 18 आदमी एक काम को 13 दिनों में पूरा कर सकते हैं, तो 54 आदमी उसी काम को कितने दिनों में पूरा करेंगे?
उत्तर जाँचने के लिए किसी विकल्प पर टैप करें।
उत्तर और व्याख्या देखें
सही उत्तर: (D) 18/4 दिन
Work = 18×13 = 234 man-days. For 54 men: 234/54 = 13/3 days.
More solved Quantitative Aptitude questions
- What will be the average of all the prime numbers before 32?
- Rs. 8400 is divided among P, Q and R in the ratio of 2/3 : 3 : 1/3 respectively. What is the share of R?
- If 72 binders can bind 720 books in 22 days, how many binders will be required to bind 660 books in 12 days?
- A person covers the first 11 km in 60 minutes and the next 22 km in 30 minutes. What is his average speed for the whole journey?
- The average of 4 numbers is 52. The average of the first two numbers is thrice the average of the other two numbers. What is the sum of…
- If a certain sum of money becomes thrice of itself in 8 years 6 months at simple interest, then what will be the annual rate of interest?