 Governance 24 October 2026

AP Cabinet Revises Polavaram Project Cost to ₹1.05 Lakh Crore, Seeks Central Grant-in-Aid of ₹58,000 Crore

పోలావరం ప్రాజెక్టు సవరించిన వ్యయం ₹1 లక్ష కోటిగా నిర్ణయించిన ఏపీ కేబినెట్; కేంద్రం నుండి ప్రత్యేక నిధుల కోసం విజ్ఞప్తి

Share𝕏fin

AMARAVATI, October 24 — The Andhra Pradesh Cabinet, chaired by Chief Minister N. Chandrababu Naidu, approved the revised cost estimate for the Polavaram Multipurpose Irrigation Project at ₹1,05,472 crore (at 2026 prices), representing a 38% increase over the 2017 estimate of ₹55,548 crore. The Cabinet simultaneously resolved to formally petition the Union Ministry of Jal Shakti for ₹58,000 crore in Grant-in-Aid citing cost overruns caused by geological challenges and tribal rehabilitation mandates.

Background: Polavaram as a National Project

Polavaram is the only irrigation project in Andhra Pradesh accorded National Project status under Section 90 of the AP Reorganisation Act, 2014 — legally obligating the Central Government to bear its entire construction cost. The project straddles the Godavari river at the AP-Odisha-Chhattisgarh tri-junction and involves:

- Irrigation: 7.20 lakh hectares across East Godavari, West Godavari, Krishna, Vishakhapatnam, and NTR districts - Hydropower: 960 MW installed capacity (12 generating units of 80 MW each) - Drinking water: Supply to 540 habitations and 29.52 lakh people in 3 municipal corporations - Navigation: Linkage to IWAI National Waterway-4 (Krishna River)

Revised DPR Breakdown (WAPCOS, 2026)

| Component | Cost (₹ crore) | |---|---| | Civil Construction | 68,400 | | Rehabilitation & Resettlement | 18,920 | | Hydro-mechanical Works | 7,200 | | Power House (960 MW) | 5,900 | | Environmental Management | 3,800 | | Road Network & Bridges | 1,252 | | Total | 1,05,472 |

Progress & Timeline

The 5.5-km head-race tunnel through the Eastern Ghats is 74% complete. The spillway (46 radial gates) is structurally finished; gate installation is 60% complete. Earthen dam embankment is at EL+40 m against the target EL+45.72 m (Full Reservoir Level). The project is targeted for first impoundment in Kharif 2028.

Tribal Rehabilitation (The Core Challenge)

1,06,480 tribal families from 371 villages across Polavaram mandal face submergence. The AP Tribal Welfare Department has constructed 14,500 houses at 8 resettlement colonies, with 68% of affected families relocated. The Supreme Court-mandated Environmental Compliance Cell has cleared 228 of 371 villages for displacement.

Central-State Dispute

The Centre had released ₹10,700 crore till 2023-24 under the National Project grant head. AP's updated demand of ₹58,000 crore (the remaining balance at revised estimates) is pending approval of the revised DPR before the Central Water Commission (CWC) Technical Advisory Committee.

Exam Relevance: APPSC Group-1 Mains (GS Paper I — Geography of AP; GS Paper II — Centre-State Relations; GS Paper III — Water Resources). APPSC Group-2 Prelims (AP Economy & Current Affairs). AP Police SI, DSP exams (General Studies). Key facts to remember — National Project status: AP Reorganisation Act 2014; River: Godavari; Capacity: 960 MW + 7.2 lakh ha irrigation; Revised cost: ₹1,05,472 crore; Location: Polavaram, West Godavari district.

తెలుగులో (Telugu Summary)

అమరావతి, అక్టోబర్ 24 — ఆంధ్రప్రదేశ్ కేబినెట్ పోలావరం బహుళార్థ సాధక ప్రాజెక్టు సవరించిన వ్యయ అంచనాను ₹1,05,472 కోట్లుగా ఆమోదించింది. ముఖ్యమంత్రి చంద్రబాబు నాయుడు అధ్యక్షతన జరిగిన కేబినెట్ సమావేశంలో కేంద్రానికి ₹58,000 కోట్ల గ్రాంట్-ఇన్-ఎయిడ్ కోసం విజ్ఞప్తి చేయాలని నిర్ణయించారు.

AP పునర్వ్యవస్థీకరణ చట్టం 2014 ప్రకారం పోలావరం జాతీయ ప్రాజెక్టుగా గుర్తింపు పొందింది. గోదావరి నదిపై నిర్మిస్తున్న ఈ ప్రాజెక్టు 7.2 లక్షల హెక్టార్ల వ్యవసాయ భూమికి నీటి పారుదల, 960 MW జలవిద్యుత్ ఉత్పత్తి, తాగునీటి సరఫరాకు ఉద్దేశించబడింది.

WAPCOS తయారు చేసిన సవరించిన DPR ప్రకారం 2026 ధరల ప్రకారం మొత్తం వ్యయం ₹1,05,472 కోట్లు. 1.06 లక్షల గిరిజన కుటుంబాల పునరావాసం 2027 నాటికి పూర్తి చేయాలని లక్ష్యం. ప్రధాన సొరంగం (5.5 కి.మీ.) మరియు స్పిల్‌వే నిర్మాణం 2028 నాటికి పూర్తవుతుందని అంచనా.

పరీక్ష ప్రాముఖ్యత: APPSC గ్రూప్-1 (నదీ ప్రాజెక్టులు, ఏపీ ఆర్థిక వ్యవస్థ), గ్రూప్-2 (ఏపీ జల వనరులు), ఏపీ పోలీస్ SI. GS పేపర్-1 (భూగోళ శాస్త్రం), GS పేపర్-2 (పాలన, రాష్ట్ర-కేంద్ర సంబంధాలు).

Source: AP Cabinet / AP Water Resources Department

Share:𝕏fin

Quick Revision Practice

Practice 5 quick questions based on recent current affairs and exam notifications to check your preparation.

Q1. Which organisation released the official recruitment notification for 11,403 Clerk posts in August 2026?

Q2. Who won India's first-ever Judo Gold medal in Commonwealth Games history during Glasgow 2026?

Q3. What is the total financial outlay approved by the Union Cabinet for the "Samudra Manthan" offshore energy scheme?

Q4. The Andhra Pradesh government rescheduled the Phase-2 Job Calendar notifications to which date?

Q5. Which state government launched the "Delhi Lakshmi Yojana" offering ₹2,500 monthly transfer to women?