11 men can complete a work in 18 days. If 1 man does the work of 2 women, find the time taken by 6 women to complete the same work.

From a SSC CHSL Tier-1 Quantitative Aptitude practice set · Quantitative Aptitude

Tap an option to check your answer.

Show answer and explanation

Correct answer: (D) 66.0 days

Total work in man-days = 11x18 = 198. In woman-days = 198x2 = 396. Time for 6 women = 396/6 = 66.0 days.